Why is task estimations and remaining work not being synchronized between Forecast and DevOps?
Answer
To synchronize remaining work between Forecast and DevOps you have to change the Forecast project setting to not calculate the remaining time automatically. To do so, head to the project's settings page in Forecast, click on the Task tab and scroll down to the "Remaining Work Estimate" options. Check the box next to Manually and it is all set.