JIRA epics come over to Forecast as phases. How can we bring them over to Forecast as tasks instead?
Answer
For JIRA epics to come over to a Forecast project as subtasks the option under ''Sync Forecast phases as'' must be set to Versions/Releases. This will allow for JIRA epics to come to Forecast as tasks.