Will reported time from a task appear on the schedule people heatmap?
Answer
The answer here depends on what exactly you would like to see in the schedule heatmap and how often your team members log time. If your team members do not log time often and you use either project allocation or task estimates then the registered time will not appear on the schedule. If, however, your team members log time regularly and you make use of time registrations and remaining task estimates then the schedule's heatmap will be calculated from the time registrations from past dates and remaining task estimates for current and future dates.